The % Completed Work fields contain the current status of a task, a resource or an assignment expressed as the percentage of the work that has been completed. You can insert the percentage of the completed work or cause the Project to calculate it based on the actual work.
Its calculation has the following formula:
Work completed = (Real Work / Work) * 100
Example: The "Writing proposed" task is scheduled for 40 hours of work. To date, the resources allocated indicate 10 hours of real work spent on the task. The Project estimates that the task has 25 percent of the work completed.
In addition, the task "To hold meetings with customers" is scheduled for 32 hours of work. The resources allocated indicate that 16 hours of work has already been spent. In the field % of Work Finished, you enter 50. The Royal Labor field changes to 16 hours.
The completion % fields contain the current status of a task, expressed as the percentage of the duration of the task that was completed. You can insert the completed percentage or cause the Project to calculate it based on the re al duration.
Its calculation has the following formula:
Percentage completed = (real duration / duration) * 100
Example: The "Proposed Editing" task was scheduled to last 10 days. The resources allocated have been working on the task for five days. The Project calculates what and the task is 50 percent completed.
In addition, you had estimated a three-day duration for the task "Driving meetings with customers". The resources allocated reported that it was completed. In the %Completed field, type 100. The Real Duration field changes to 3 days and the Real Term field changes to the scheduled end date.