← Back to the blogProject and Portfolio Management

Project status by email in PSA Easy: what needs your attention?

Article summary

What you will find here

Use visual management in PSA Easy to compare progress and finish dates, prioritize a task and identify who needs to act from the project status email.

Leandro Lima presents the PSA Easy status email, showing indicators and tasks for a demonstration project. The email is shown in Portuguese.
PSA Easy demonstration screen (email in Portuguese). The portal calculation example appears below.

01Check the reporting date first

Before following up on a delivery, check the project name, project manager and reporting date in the header. The email shows what was on record when the report was generated. Select the project name to open it in PSA Easy and check for updates.

The example below follows a fictional portal rollout. MLPro verified this version of the report in a development environment. Its availability depends on your organization’s environment.

02Read progress in percentage points and finish variance in days

By the reporting date, the portal rollout was due to be 60% complete. Completed progress was 48%. Subtract planned progress from completed progress: 48 minus 60 gives −12 percentage points. That tells you how far the project was behind its progress target on that date. The Portuguese email displays this value in the Diferença (difference) field with a % sign. It represents a difference in percentage points.

Now check the finish variance. In this example the report shows +3 days, which means the current finish date is three days later than the baseline finish date. The two figures answer different questions. The progress gap shows how much planned work is behind, and the finish variance shows how far the finish date has moved from the baseline. A project can be behind on progress and still hold its finish date, or the other way round. If the finish variance is blank, the comparison is unavailable. Zero days means the two finish dates match.

Portal rollout · Fictional example
Planned progress60%
Completed progress48%
Progress gap−12 percentage points
Finish variance+3 days

In the video, the first project shown has 70% planned and 19% completed. Completed progress is 51 percentage points below plan, and the finish variance is 187 days against the baseline.

03Find the task that is holding up the next delivery

With the project behind its progress target and the finish three days past the baseline, the next step is to find the task behind the delay.

The email groups tasks into overdue, in progress, upcoming and recently completed. Compare the total count with the number of rows shown. Upcoming tasks start after the reporting date and are due within the following seven days. Recently completed tasks cover the previous seven days.

In the portal rollout, access validation is overdue and the team needs it before testing can begin. That dependency gives the project manager a reason to tackle it first. Selecting the task name opens its record, where the manager can check progress before calling the owner. The link to the project’s tasks opens the full section.

Planned progress is 60% and completed progress is 48%, a gap of −12 percentage points. The forecast finish is three days later than the baseline. Access validation is overdue.
In the portal example, the progress gap and finish variance help identify which task to check.
Real capture of the PSA Easy status email, in Portuguese, showing 70% planned, 19% completed, a −51% gap and a finish variance of 187 days, and the overdue block with 11 tasks. The Testes do Ambiente task name is highlighted, and an arrow leads to the same task opened in PSA Easy, with name, start and finish. Project name, manager and owners hidden by gray bars.
Status email for the project shown in the video: the overdue task name opens its record in PSA Easy. Interface in Portuguese; project name and owners hidden.

04Give each risk or issue a response and an owner

As long as loss of access to the test environment was a possibility, it was a risk. Once the environment became unavailable and blocked validation, the team had an issue to resolve. Check the records for what happened and the response the team agreed on.

In this example the environment owner has the next action: restore access and let the person running validation know. Open the linked action plan to check its owner and due date. If there is no plan yet, the project manager can agree on a response with the team. The PMO can follow up if the issue affects other projects.

05Use change requests and the project log to make the decision

Before asking the sponsor to move a milestone, check whether a change request already covers it and what stage it has reached. The project log gives context for earlier decisions. In the portal example, a log entry could explain why the team decided to wait for access validation before starting tests.

When the sponsor needs to decide, set out the milestone impact, the options and when the decision is due. The person following up can select the item name to open its record or use the group link to open the relevant project section. Each person’s permissions apply. At the next review, check whether the action is complete and whether the forecast finish date has changed.

Leandro Lima, Nathalia Souza and Ricardo Sabino wrote the original article about Project Online in 2022. Leandro Lima and Renata Yatsu updated it for PSA Easy on November 24, 2026. See the original Project Online report design update.

Talk to a specialist

Want to understand PSA Easy for your portfolio?

Tell us what you need. Leave your name and email to discuss the next step with MLPro.

Fast response, no-obligation conversation.
Add information optional